Change request · CR-003 · Proposed

Add event history without moving the production gate

A seven-day operator history panel adds 3 engineer-weeks; the recommended trade preserves 2026-11-02.

Baseline versus requested change

Baseline

Live state only

The operator overview shows current queue status and links to the runbook.

Impact ledger

Effort3 engineer-weeks
ProductionStays 2026-11-02 under option 1
QualityDesign-handoff acceptance required
BaselineRFC 014 and 24 engineer-weeks until approval