Delivery plan · Amber
Five gates carry RFC 014 from decision to handoff
The 24 engineer-week baseline runs from 2026-08-31 to 2026-11-20; decision and environment ownership remain the active dependencies.
Milestone rail
- Design accepted
RFC 014 and requirements bind delivery.
- Chaos environment ready
RAID-01 closes or the forecast moves.
- Staging dual-write
Both paths observed before cutover.
- Readiness decision
Evidence and waivers reviewed.
- Production to handoff
Cutover, hypercare, close on 2026-11-20.
Workstream board
Runtime
Platform: dispatcher, queues, consumers.
Assurance
Reliability: failure behavior and gate.
Producers
Checkout, Catalog, Inventory fixtures by 2026-10-16.