Basis of estimate · 2026-08-26
The split path is a 24 engineer-week commitment
Expected effort is 24 engineer-weeks, with a 22–28 engineer-week range and medium confidence.
24engineer-weeks expected
22–28engineer-week range
Mediumconfidence
Work breakdown
| Work | Engineer-weeks |
|---|---|
| Dispatcher and queues | 9 |
| Consumers and observability | 6 |
| Testing and readiness | 5 |
| Cutover and handoff | 4 |
What the estimate assumes
The API, authentication, warehouse schema, batch path, and retention remain unchanged. The chaos environment is ready by 2026-09-18.