Delivery status · Period ending 2026-08-26
Delivery is Amber while decision and chaos ownership remain open
The 2026-11-02 forecast remains achievable if the 2026-09-01 decisions and 2026-09-18 environment gate close.
OverallAmberdecision + environment dependency
Forecast2026-11-02unchanged
Baseline24engineer-weeks
This period
Discovery closed, RFC 014 reached proposal, requirements were identified, and the five-gate delivery baseline was drafted.
Attention required
- Platform director decides RFC 014 by 2026-09-01.
- Platform confirms the chaos environment owner and 2026-09-18 gate.
- Reliability decides RAID-02 by 2026-09-01.
Next period
Mobilise Platform, baseline 24 engineer-weeks, confirm traceability, and accept or move staging. CR-003 stays outside scope.