Delivery status · Period ending 2026-08-26

Delivery is Amber while decision and chaos ownership remain open

The 2026-11-02 forecast remains achievable if the 2026-09-01 decisions and 2026-09-18 environment gate close.

OverallAmberdecision + environment dependency
Forecast2026-11-02unchanged
Baseline24engineer-weeks

This period

Discovery closed, RFC 014 reached proposal, requirements were identified, and the five-gate delivery baseline was drafted.

Attention required

  • Platform director decides RFC 014 by 2026-09-01.
  • Platform confirms the chaos environment owner and 2026-09-18 gate.
  • Reliability decides RAID-02 by 2026-09-01.

Next period

Mobilise Platform, baseline 24 engineer-weeks, confirm traceability, and accept or move staging. CR-003 stays outside scope.